HOUSING AND LAND USE REGULATORY BOARD
Regional Field Office - Bicol Region
LIST OF PROJECTS ISSUED CEASE AND DESIST ORDER and CDO LIFTED
NAME OF PROJECT LOCATION DEVELOPER   CDO DATE
    LIFTED
      DATE ISSUED REMARKS  
70-DOOR TENEMENT HOUSING Bgy. Bitano, Legazpi City Simon M. Brizuela 29-Oct-15 No CR/LS (Pre-Selling) Not yet
        No Advertisement Approval Lifted to date
EL POBLACION DE LEGAZPI Bgy. Bitano, Legazpi City Simon M. Brizuela 21-Sep-15 No CR/LS (Pre-Selling)  
        No Advertisement Approval -do-
ECS LAND RESIDENCES Puro, Legazpi City Ysmael V. Abo/ 21-May-15 CDO from further collecting -do-
    EFX Creative Studio   amortization payments from buyers  
ECOHOMES BAYSHORE  Puro, Legazpi City Sunwestville Realty 17-Apr-15 No PALC/DP, CR/LS  
CONDOMINIUM   & Dev't Corp   CDO from further undertaking  -do-
        advertising activities  
CITI HEIGHTS RESIDENCES LEGAZPI Sitio Guyam, Bgy. Taysan, Jesus C. Palma,Jr. 19-Mar-15 CDO from advertising activity  
  Legazpi City Mayon Monte Vista Heights Inc.     -do-
CITI HEIGHTS RESIDENCES LEGAZPI Sitio Guyam, Bgy. Taysan, Jesus C. Palma,Jr. 06-Feb-13 CDO from selling activity -do-
  Legazpi City Mayon Monte Vista Heights Inc.      
GERALDINE VILLAGE (MAIN & SHP) Libtong, Tiwi, Albay Geraldine M. Chiong 16-Oct-14 Incomplete Development -do-
         
LA VERDE SUBDIVISION San Jose, Malilipot, Albay Eufrocina G. Llovido 30-Jun-14 Incomplete development; no concrete  
      measures undertaken re: deficiency in -do-
        water supply within the subd. Project.  
ECS RESIDENCES PHASE III Bgy. Moyod, Old Albay,  Mr. Ysmael V. Abo/ 11-Jul-14 No PALC/DP/ CR/LS -do-
  EFX Creative Studio   No Adv. Approval  
  Maonon, Ligao City Mr.Nicanor  03-Jul-14 No PALC/DP/ CR/LS -do-
    Sto.Tomas, Jr.      
ECS RESIDENCES PHASE II Bgy. Moyod, Old Albay,  Ysmael V. Abo 07-Jul-14 No PALC/DP/ CR/LS -do-
  Legazpi City EFX Creative Studio   No Adv. Approval  
VILLLA ROSITA SUBDIVISION Pangol St., Bgy. Tinago,  Holy Gate Homes 11-Jun-14 No PALC/DP/ CR/LS -do-
  Ligao City     No Adv. Approval  
SUBDIVISION PROJECT (RES'L LOTS) Pawa, Tabaco City Ms. Ireen Raginio 14-Apr-14 No PALC/DP/ CR/LS -do-
           
ECS LAND RESIDENCES Puro, Legazpi City Ysmael V. Abo/ 09-Sep-13 CDO from further conducting selling and -do-
    EFX Creative Studio   advertisement activities  
VILLA DE STA. MONICA Taysan, Legazpi City Ysmael V. Abo/ 09-Sep-13 CDO from further conducting selling and -do-
    EFX Creative Studio   advertisement activities  
VILLA JEMENA Villa Hermosa, Daraga, Ysmael V. Abo/     -do-
  Albay EFX Creative Studio      
SUBDIVISION PROJECT Anislag, Daraga, Albay Leonardo M.Olivarez 28-May-13 Pre-selling; No PALC/DP; CR/LS -do-
    LMO Realty Services      
ECS RESIDENCES PHASE I Bgy. Moyod, Old Albay, Legazpi City       -do-
    Ysmael V. Abo 15-Jan-13 No PA/LC; No CR/LS  
GLORIA DREAM HOMES SUBDIVISION Anislag, Daraga, Albay Mr. L. Olivarez 07-Jan-13 (Portion of subdivision) -do-
        No amendment of CR/LS  
CAMELLA LEGAZPI Estanza, Legazpi City   25-Sep-12 CDO from conducting further  -do-
        Advertisement Activity; No PALC/DP;   
        No CR/LS; No Advertisement Approval  
OUR GARDEN OF FAITH MEMORIAL Sugcad, Polangui, Albay Mr. Arnold Embestro 10-Sep-12 Lapsed EOTD/ Incomplete -do-
PARK       Development  
MAYON RIVIERA SUBDIVISION Lidong, Sto. Domingo, Albay Mr. Donato G. Lopez,Jr. July 2012 No EOTD; Failed to submit ECC and clearance -do-
        from the Phil. Institute of Volcanology &  
        Siesmology  
CMP / CMP PROJECT Bgy. Layon, Ligao City Mr. John Sison/   No PALC/DP; No CR/LS -do-
    Ramfer Builders &  30-Apr-12  
    Dev't Corp.      
ITARAN SUBDIVISION PROJECT Bgy. Itaran, Polangui, Albay Francisco C. De Borja  19-Oct-11 Pre-selling; No PALC/DP; CR/LS -do-
           
ANNIE HILLS SUBDIVISION  (OM) Anislag, Daraga, Albay EA Ygoña Const.& 10-Sep-11 Suspension of License due to lapsed -do-
    Dev't Corp. (LS suspension) of prescribed period to complete dev't  
        per letter dated 13 September 2011  
      18-Nov-11 CDO from selling & collecting amortization -do-
        payments  due to incomplete dev't  
ANNIE HILLS SUBDIVISION  (SHP) Anislag, Daraga, Albay EA Ygoña Const.& 10-Sep-11 Suspension of License due to lapsed -do-
    Dev't Corp. (LS suspension) EOTD per letter dated 13 Sept 2011  
      18-Nov-11 CDO from selling & collecting amortization -do-
        payments  due to incomplete dev't  
ST. GREGORY SUBDIVISION Barangay Tula-Tula Vilma Delayre-Ante 05-Oct-11 No PALC/DP; Pre-selling (No CR/LS) -do-
  Legazpi City AVY Land Dev't and Management Resource Service      
TABACOVILL HOMEOWNERS  ASS'N Cabangan, Tabaco  Mr. John Sison/ 18-Apr-11 CDO due to Pre-Selling  -do-
           SUBDIVISION PROJECT City JN Sison Real Estate       
    Consultancy Services      
CENTRAL CITY SUBDIVISION PHASE I Bitano, Legazpi City Imperial Homes  29-May-11 Expired EOTD; Inc. Dev't  
    Corporation (LS Suspension)   -do-
           
ST. ROCHE SUBDIVISION Taysan, Legazpi  Ms. Vilma Del Ayre-ante/ 28-Jun-10 CDO due to Pre-Selling -do-
  City AVY Land Dev't & Mgt.      
    Resources Services      
COMMUNITY MORTGAGE PROGRAM/ Maslog, Legazpi Ms. Vilma Del Ayre-ante/ 29-Jun-10 CDO due to Pre-Selling -do-
SOCIALIZED HOUSING PROJECT City AVY Land Dev't & Mgt.      
LOT 977-A-I-F (Portion of Lots within  Tahao Rd., Legazpi  DELLARC Realty & Devt 04-Jun-10 CDO due to Selling of add'l lots without  
Centerpoint Subdivision) City Company   License due to unauthorized alteration of lot -do-
GREEN VALLEY SUBDIVISION Guyam, Taysan, Legazpi  Ysmael V. Abo/ 23-Oct-09 CDO due to Pre-Selling   
  City AVY Land Dev't & Mgt.     -do-
    Resources Services      
PARKLAND SUBDIVISION (M & SHP) Banao, Guinobatan, Juan Garcia 07-Jul-09 CDO due to Incomplete Development/ -do-
  Albay     Unauthorized Alteration  
PONSO HEIGHTS SUBDIVISION Ponso, Polangui,  Polangui Villagers 12-Aug-11 CDO due to Incomplete Development/ -do-
  Albay Realty corp   Non-payment of fine  
VALLE DEL MAR SUBDIVISION (M&SHP) Puro, Legazpi  Optimus Ventures 29-May-08 CDO due to Incomplete Development/ -do-
  City     Non-payment of fine  
SERENITY MEMORIAL PARK/CEMETERY Bgy.3,Centro, Camalig, Ms. Mercy Guiriba- 10-Dec-07 CDO due to No PALC/DP & CR/LS -do-
  Albay Sangil      
ST. JAMES SUBDIVISION (M & SHP) Tamaoyan, Legazpi City Cesar Bordeos, Jr. 19-Sep-06 CDO due to Incomplete Development -do-
CHERRY HOMES SUBDIVISION (M&SHP) Cararayan, Tiwi, Albay Ma.Cherry Ruiza Acuña 09-Oct-06 CDO due to Incomplete Development/ -do-
        Pre-Selling (lots resulting from  
        the unauthorized alteration of lots  
STA. MONICA HEIGHTS SUBDIVISION Taysan, Legazpi City Sta.Monica Heights Dev't 08-Oct-01 CDO due to Incomplete Development -do-
(Main & SHP)   Corp/Antonio Paguirigan & 04 Jan 06    
NOVA CENTRO VILLAS EXECUTIVE HOMES Gov.Forbes St.San.Roque,        
Old Name: NOVA CENTRO EXEC.VILLAGE Legazpi City Norman Yu 09-Dec-04 CDO due to Pre-Selling w/o LS -do-
      23-May-05 CDO due to Advertising without  
        Approval  
JMM SUBDIVISION (M&SHP) Rawis, Legazpi City John M. Mercado 10-Aug-04 CDO due to pending case(regular court) -do-
LA FELICIDAD MEMORIAL PARK/CEMETERY Quirangay, Camalig,  Ms.Nineveth Garcia 06-Jan-90 CDO's due to Pre-Selling  
  Albay   &16 Sept 03   -do-
GUINOBATAN PALM VILLAGE (M&SHP) Travesia, Guinobatan,Albay David Imperial 04-May-99 Incomplete Dev't./with pending case -do-
        (Portion)  
SEAVIEW ESTATE SUBDIVISION Buraguis, Legazpi City Engr. Manuel Bolinas 29-Oct-99 CDO due to Incomplete Development -do-
BEL-AIR SUBDIVISION Bonot, Legazpi City Lilian Gimenez 12-May-98 CDO due to Conflict of ownership/ -do-
        Incomplete Development  
TABUENA HOMELOTS Pinaric, Legazpi City Dra. Angustias D. 17-Nov-98 Incomplete Development -do-
    Calleja      
TABUENA HOMELOTS Maoyod, Legazpi City Dra. Angustias D. 14-May-96 Incomplete development -do-
    Calleja      
SEVEL VILLAGE SUBDIVISION Poblacion, Daraga, Albay Quintin Segovia-Owner 09-Jan-07 Incomplete development -do-
    Francisco Velasco-Dev      
 
OUR LADY'S VILLAGE Phase 3 (Portion C) Pangpang, Sorsogon City OLV Foundation, Inc. 14-Aug-07 CDO due to Incomplete Development -do-
      6/18/2012 (LS Suspension) LS Suspension due to Incomplete Dev't  
ST. VINCENT SUBDIVISION PH.2 Bulan, Sorsogon Ocean Biodynamics Corp. 13-Mar-07 CDO due to Incomplete Development -do-
HOLY GATE HOMES Ph.2 (M&SHP) Cambulaga, Sorsogon City Jesus Bagasina 25-Aug-06 CDO due to Incomplete Development  
ST. FRANCIS HOMES Juban, Sorsogon Teoton Realty & Dev't 18-May-99 CDO due to Incomplete Development -do-
    Corporation   and Non Payment of Fine  
SORSOGON EXECUTIVE VILLAGE PH.I Tugos, Sorsogon City Galver Construction 23-Nov-04 CDO due to unapproved alteration of plan -do-
TIONGZON SUBDIVISION Ibingay, Masbate City Amelia P. Ramirez 09-Oct-02 CDO due to Incomplete Development -do-
PHASE V          
NONE          
STONEHILL SUBDIVISION (OM, EH, SHP) Tawig, Paracale, Cam. Norte Cosmoservice 11.16.15 CDO from further dev't of the subd.proj. -do-
    Resource Dev't Corp   upon resolution of complaint   
 MEMORIAL PARK OF THE RISEN CHRIST  Mancruz, Daet, Cam. Norte  Engr. Gilbert R. Caringal  14- Sept.-10 CDO due to Incomplete Development -do-
           
 OUR LADY'S VILLAGE PH. II  Pangpang, Sorsogon City  Our Lady's Foundation  05-Oct.-11  CDO due to non-application of CR/LS -do-
 BIENVILLE HOMES (Main)  Rizal, Prieto Diaz, Sorsogon  Dra. Jocelyn Y. Lelis  11-Oct.-11 (LS Susp.)  LS Suspended due to incomplete Devt. -do-
 BIENVILLE HOMES (SHP)  Rizal, Prieto Diaz, Sorsogon  Dra. Jocelyn Y. Lelis  11-Oct.-11 (LS Susp.)  LS Suspended due to incomplete Devt. -do-
 EMERALD HOMES- DAET (SHP)  Alawihao, Daet, Cam. Norte  Victor C. Varin  02-March-12 (LS Susp)  LS Suspended due to incomplete Devt. -do-
FLORIDA VILLAGE (M&SHP) Lag-on, Daet,Cam.Norte Carlos S. Malonzo 11-Mar-09 CDO due to Incomplete Development -do-
GINTONG HIMLAYAN MEMORIAL PARK Sta. Rosa Sur, J. Panganiban Eduardo A. Herce 30-Mar-11 CDO due to Incomplete Development -do-
  Camarines Norte        
BLOOMINGDALES HOMES SUBD. (SHP) Malasugi, Labo, Cam.Norte Edwin L. Villagomez 13-Aug-07 CDO due to Incomplete Development -do-
TOWNSVIEW HOMES SUBD. (M&SHP) Poblacion, Sta Elena,   13-Aug-07 CDO due to Incomplete Development -do-
  Camarines Norte        
PEJO SUBDIVISION Bgy. Gimaga, Goa, Camarines Atty. Rosario Pejo 19-Jan-16 No CR / LS -do-
  Sur Buelva      
RESIDENTIAL SUBDIVISION PROJECT Zone 7, San Benito, Goa Mr. Jose Otero 18-Sep-14 No PALC/DP; CR/LS; CDO from selling activities -do-
  Camarines Sur        
PRIVATE CEMETERY Barangay San Pascual, Mr. Noel Tuy Borja 03-Jun-13 No PALC/DP; CR/LS -do-
  Tinambac, Camarines Sur   CDO from conducting further operation, burial,  
      and pre-selling activities  
STA. RITA SUBDIVISION Barangay Sagurong, Pili, Agerico L. Marasigan 26-Apr-06 CDO from collecting amortization from buyers  -do-
(Main Project and SHP Counterpart) Camarines Sur     and  selling activities, due to incomplete dev't.  
PASEO DE SAN IGNACIO Barangay Pacol, Naga City AVIDA Land Corp. 01-Aug-12 Suspension of LS due to incomplete -do-
(Commercial)     (LS Suspension) development  
 JARDINEL MEMORIAL PARK Bgy. Sagrada Familia, Bula, Felix Jardinel 14 Feb. 2013 No PALC/DP; CR/LS -do-
  Camarines Sur   CDO from further construction & dev't  
      & from further burial and pre-selling  
      activities  
SUBDIVISION OF LOT 2019, CAD-435-D Bgy. Sta. Lucia, Magarao, Herbert and Annalyn  26-Aug-11 CDO due to No PALC, DP, CR and LS -do-
  Camarines Sur Toledo      
OUR LADY OF LA PORTERIA MEMORIAL Bgy. San Isidro, Calabanga, Joseph C. Bienvenuto 09-Dec-09 CDO due to No PALC, DP, CR and LS -do-
GARDEN Camarines Sur        
KATONINONGAN MEMORIAL GARDEN Bgy. Danlog, San Jose, Dolores D. Reynes 03-Dec-10 CDO due to No PALC, DP, CR and LS -do-
  Camarines Sur        
SUBDIVISION OF LOT-C-PSD-05-040080 Bgy. Sta. Lucia, Magarao, Amalberga R. Blasa 27-Sep-10 CDO due to No PALC, DP, CR and LS -do-
  Camarines Sur        
BICOL HEAVEN'S GRANDUER MEMORIAL Bgy. San Francisco, Ocampo, Earlyn P. Peyra 06-Aug-07 CDO due to No PALC, DP, CR and LS -do-
PARK Camarines Sur        
NAGA IMPERIAL CREMATORY AND Zone 5, Bgy. Balatas, Balatas Mega Imperial Dev't. 07-Jul-11 CDO due to No CR, LS and  -do-
COLUMBARIUM Road, Naga City Group, Inc.   Advertisement Approval  
NAGA GREENPARK VILLAGE SUBDIVISION Bgy. Del Rosario, Naga City Enjoy Realty & Dev't.,  15-Aug-11 CDO due to Incomplete Development -do-
(SHP Counterpart)   Corporation 3/9/2006(LS Susp) Suspension of LS per letter dtd 8/15/11  
MARINER'S VILLAGE Bgy. Sta. Lucia, Magarao, MAP Landholdings & 25-Jan-13 CDO due to Incomplete Development -do-
(Main Project) Camarines Sur Real Estate Dev't., Inc.      
MARINER'S VILLAGE PHASE ii Bgy. Sta. Lucia, Magarao, MAP Landholdings & 25-Jan-13 CDO due to Incomplete Development -do-
(Main Project) Camarines Sur Real Estate Dev't., Inc.      
SAN FERNANDO VILLAGE  Bgy. Pamukid, San Fernando, First Vicion Realty, Inc. 06-Feb-09 CDO due to Incomplete Development -do-
(SHP Counterpart) Camarines Sur   13-Sep-07 Suspension of License per letter  
      (LS Suspension) dated 21 July 11  
HEAVEN'S GARDEN MEMORIAL PARK Bgy. Ibid, Libmanan, Ventura Dev't. Corp. 21-Jun-08 Incomplete Development -do-
PHASE I Camarines Sur   (LS Suspension) Suspension of LS per letter dtd 9/8/11  
MVJ FORTUNE HILLS SUBDIVISION  Libmanan, Camarines Sur Skylite Philippines, 09-Jul-08 CDO due to Incomplete Development  
(Main Project and SHP Counterpart)   Incorporated      
MONTE CIELO DE NAGA PHASE III Bgy. Del Rosario, Naga City Fil-Estate Properties, 11-Jun-09 Incomplete Development 07-Sep-15
(Main Project)   Incorproated (LS Suspension) Suspension of LS dtd 9/8/11  
AEROVILLE HOMES PEÑAFRANCIA Bgy. San Felipe, Naga City R & I Resource Mgt., 08-Jun-07 CDO due to Incomplete Development -do-
(Main Project and SHP Counterpart)   Incorporated   and Non-payment of admin. fine  
MILAOR VILLAS  Bgy. Capucnasan, Milaor, Fil-Estate Properties, 27-Sep-09 Suspension of LS due to incomplete 07-Sep-15
(SHP Counterpart) Camarines Sur Incorporated (LS Suspension) development  
RESIDENTIAL SUBDIVISION PROJECT Bgy. Caraycayon, Tigaon, Mrs. Narita Reyes 09-Nov-12 CDO due to no PALC, DP, CR and LS -do-
  Camarines Sur        
CACERES HEIGHTS RESORT SUBDIVISION Bgy. Pacol, Naga City Jamaica Realty and 09-Nov-12 Suspension of LS due to incomplete -do-
(Main Project and SHP Counterpart)   Marketing, Inc. (LS Suspension) development  
RAMOS MEMORIAL PARK Bgy. San Vicente, Lagonoy, Mr. Willy Ramos 09-Nov-12 CDO due to no PALC, DP, CR and LS -do-
  Camarines Sur        
FRANCISVILLE SUBDIVISION  Bgy. San Isidro, Sangay Mr. Jesus Bagasina 20-Jun-07 CDO due to Incomplete Development -do-
(SHP Counterpart) Camarines Sur        
CALABANGA MEMORIAL PARK Bgy. San Isidro, Calabanga, Mrs. Erlinda M. Ustaris 31-Jul-09 Incomplete Development - -do-
  Camarines Sur   (LS Suspension) Suspension of LS per letter dtd 9/8/11  
           
SALES SUBDIVISION Bgy. Paolbo, Calabanga, Mrs. Flor Vda. De Sales 30-Jun-08 CDO due to No PALC, DP, CR and LS -do-
  Camarines Sur        
STA. CLARA VILLAGE  Bgy. Gubat, Tigaon, Jamaica Realty and 29-Jun-04 CDO due to Incomplete Development; -do-
(Main Project and SHP Counterpart) Camarines Sur Marketing, Inc.   Cancelled CR/LS on 10/20/09  
MONTE CIELO DE NAGA PHASE IV  Bgy. Concepcion Grande, Fil-Estate Properties, 05-Mar-01 CDO due to No Alteration Approval  -do-
(Main Project) Naga City Incorporated   from LGU  
MONTE CIELO DE NAGA PHASE I Bgy. Concepcion Grande, Fil-Estate Properties, 28-May-08 CDO due to Non-compliance with  -do-
(Main Project) Naga City Incorporated   directives per letter dated 28 May 2008  
FARMS SUBDIVISION Bgy. Paolbo, Calabanga,  Ms. Flor Vda. De Sales 30-Jun-08 CDO due to Incomplete Development -do-
  Camarines Sur        
VILLA SAGRADA HOUSING PROJECT Barangay Sagrada, Baao, Adelina I. Perdon 03-Jul-01 CDO due to Incomplete Development -do-
(Main Project and SHP Counterpart) Camarines Sur      
BATO MEMORIAL PARK Bgy. San Rafael, Bato, Cam. Sur Mrs. Susan V. De Villa 17-Apr-12 CDO due to no PALC, DP, CR and LS -do-
           
BUENAVIDA VILLAGE Bgy. Carolina, Naga City Fil-Estate Properties, 14-May-12 Suspsension of LS due to incomplete -do-
(SHP Counterpart)    Incorporated (LS Suspension) development  
SANCTUARIO DE LOS ALMAS MEMORIAL Bgy. San Francisco, Tigaon, Dra. Ma. Linda B. Llaguno 03-Jun-09 CDO due to incomplete development -do-
GARDEN Camarines Sur        
HOLY GATE HOMES - TIGAON Bgy. Talojongon, Tigaon, Mr. Jesus Bagasina 13-Nov-10 Suspension of LS due to incomplete -do-
(Main Project and SHP Counterpart) Camarines Sur   (LS Suspension) development  
CAMAGONG LEISURE FARM AND RESORT Bgy. Camagong, San Jose, Eastern Pacific Proper- 19-Mar-09 Suspension of LS due to incomplete -do-
  Camarines Sur ties, Incorporated (LS Suspension) development  
HOLY TRINITY MEMORIAL PARK PHASE II-A Bgy. San Francisco, Iriga City Mr. Estanislao O.Nuñez 10-Nov-06 CDO due to incomplete development -do-
         
CITI-HOMES SUBDIVISION  Bgy. San Nicolas, Iriga City Mr. Jose B. Marbella 02-Oct-06 CDO due to incomplete development -do-
(Main Project and SHP Counterpart)          
HARMONY HOMES Bgy. Bahay, Libmanan,  Dr. Willie V. Kho 22-Jul-10 Suspension of LS due to incomplete -do-
(Main Project and SHP Counterpart) Camarines Sur   (LS Suspension) development  
M & H DEMESA MEMORIAL PARK Bgy. San Vicente, Lagonoy, Mr. Melvin M. Demesa 20-Jun-12 CDO due to no PALC, DP, CR and LS -do-
  Camarines Sur        
TRINITY VILLAGE Bgy. Tambo (Danao), Engr. Oscar F. Nuñez 22-Oct-12 CDO due to no PALC, DP, CR and LS  
  Pamplona, Camarines Sur       -do-
RESIDENTIAL SUBDIVISION PROJECT Bgy. San Vicente-San Antonio, Mr. Remegio Manchus 05-Jun-12 CDO due to no PALC, DP, CR and LS  
  Pili, Camarines Sur       -do-
RESIDENTIAL SUBDIVISION PROJECT Bgy. Caraycayon, Tigaon, Mrs. Narita V. Reyes 09-Nov-12 CDO due to no PALC, DP, CR and LS  
  Camarines Sur       -do-
RESIDENTIAL SUBDIVISION PROJECT Bgy. Sto. Domingo, Iriga City Ms. Rebecca P. Tubig 20-Dec-12 CDO due to no PALC, DP, CR and LS  
        -do-
ALTHESA VILLAGE Barangay Tagbong, Pili, Mr. Alfredo L. Salazar 28-Sep-01 CDO from conducting further selling activities -do-
(Main Project and SHP Counterpart) Camarines Sur     due to incomplete development  
AVENGOZA SUBDIVISION  Tara, Sipocot, Camarines Sur Salvador Avengoza/ 09-Mar-99 CDO due to Incomplete Development -do-
(Main Project and SHP Counterpart)   Angelina S. Jaramillo   (applied for cancellation of   
        CR/LS; surrendered original  
        copy of CR/LS)  
As of February 2016